This building, under construction on
Booth Street East in February of 2015, is to be the
National Graphene Institute when it opens its doors
later in 2015.
The University of Manchester website explains that,
"Graphene
is a two dimensional material consisting of a single
layer of carbon atoms arranged in a honeycomb or
chicken wire structure. It is the thinnest material
known and yet is also one of the strongest. It
conducts electricity as efficiently as copper and
outperforms all other materials as a conductor of
heat. Graphene is almost completely transparent, yet
so dense that even the smallest atom helium cannot
pass through it." The connection to
Manchester is the fact that Andre Geim and
Kostya Novoselov received
several awards for their pioneering research on graphene
while at the University of Manchester including the 2010
Nobel Prize in Physics.
Jestico and Whiles, the building's architects, say on
their website that,
“The building is a compact 4
storey cube that occupies the full site foot print.
The main cleanroom is located on the lower ground
floor to achieve best vibration performance. Offices
and labs are intermixed on all floors with most of
the labs and all the offices having views and
daylight. A top lit double height breakout space
linking two floors provides welcome respite at the
heart of the intense working environment. A roof
terrace also forms part of the top floor social and
public area. ......
..... The building is enclosed by an economic
inner skin comprising a proprietary composite
cladding panel system that provides weather
tightness and thermal insulation and accommodates
flush windows and other openings as required. Fixed
to the outside of this inner skin is a separate
perforated stainless steel ‘veil’ which wraps around
the volumes of the different elements of the
building continuously to provide a unifying texture
and fluid shape. Cut-outs in the perforated steel
provide clear views out from internal spaces and
allow access for window cleaning via water fed
extendable pole or cherry picker. Gantries are
provided at 1st, 2nd & 3rd floors along the
south façade for window cleaning purposes.”
**********************
Some images from earlier in the construction phase.